PRODUCTION CALENDAR
For the 2022 Spring Festival our factory closed from 23 January to 9 February and resumed on 10 February. No shipments left the factory in that window.
The schedule as it ran
| Item |
Date |
| Last working day |
22 January 2022 |
| Factory and office closed |
23 January - 9 February 2022 |
| Work resumes |
10 February 2022 |
| Shipments during the break |
Paused |
What stopped and what kept running
As an industrial mini pc manufacturer, our production, testing, packing and outbound shipping stopped. Sales stayed reachable online for quotations, order confirmations and technical questions, which meant an inquiry sent in the middle of the break still got an answer even though nothing could be dispatched.
How buyers usually plan around it
◆ Place orders that need to ship before the break at least six to eight weeks ahead, so production and inspection finish first.
◆ Expect the two weeks after the restart to be busy: freight space and factory slots both tighten.
◆ For a new OEM housing, start oem odm services with a drawing review before the break rather than after it.
◆ Keep a small buffer of spare units for counters and kiosks that cannot go offline.
Orders already in production
Any order in production when the factory closed resumed at the same stage after 10 February. If you are planning around a similar calendar now, send us the model list and the date you need the goods on site, and we will work backwards through production and transit instead of quoting a lead time in isolation.
Check the range
The models discussed here are listed in our collections, from industrial panel PCs and kiosk hardware to retail pos hardware, with port maps and panel sizes on each product page.
◆ industrial panel PCs
◆ POS terminals
◆ self-service kiosks
If you need a drawing or a port list for a specific model, send the requirement and we will reply with the document rather than a brochure.